A project team has identified project risks. Which of the following is the NEXT step?

The correct answer is C. Communicate. In project risk management, the standard process flows as: Identify → Communicate → Prioritize → Plan → Monitor. After risks are identified, they must be communicated to relevant stakeholders before any prioritization or response planning begins. Communicating first ensures all…

Project management concepts

Question

A project team has identified project risks. Which of the following is the NEXT step?

Options

  • APrioritize
  • BPlan
  • CCommunicate
  • DReview

How the community answered

(61 responses)
  • A
    3% (2)
  • B
    2% (1)
  • C
    89% (54)
  • D
    7% (4)

Explanation

In project risk management, the standard process flows as: Identify → Communicate → Prioritize → Plan → Monitor. After risks are identified, they must be communicated to relevant stakeholders before any prioritization or response planning begins. Communicating first ensures all stakeholders are aware of the risks, can provide input, and that no decisions are made in a vacuum. Skipping communication could mean risks are prioritized or addressed without full organizational awareness or buy-in.