PK0-004 · Question #886
The project manager for a multinational project is evaluating the option of scheduling face-to-face meetings during the release of a new system. The goal is to provide 24/7 coverage and quick…
The correct answer is D. Risk mitigation. Risk mitigation involves taking proactive actions to reduce the probability or impact of a risk. By scheduling face-to-face meetings and establishing 24/7 coverage, the project manager is reducing the potential impact of issues that arise during the system release - ensuring…
Question
The project manager for a multinational project is evaluating the option of scheduling face-to-face meetings during the release of a new system. The goal is to provide 24/7 coverage and quick responses to issues. Which of the following strategies is being applied?
Options
- ARisk acceptance
- BRisk avoidance
- CRisk transference
- DRisk mitigation
How the community answered
(48 responses)- A8% (4)
- B2% (1)
- C15% (7)
- D75% (36)
Explanation
Risk mitigation involves taking proactive actions to reduce the probability or impact of a risk. By scheduling face-to-face meetings and establishing 24/7 coverage, the project manager is reducing the potential impact of issues that arise during the system release - ensuring rapid response and resolution. This is not risk avoidance (which would mean not doing the release), not risk transference (which would shift the risk to a third party), and not risk acceptance (which would mean acknowledging the risk but taking no action). Structured coverage is a classic mitigation strategy.
Topics
Community Discussion
No community discussion yet for this question.