Question

The project manager for a multinational project is evaluating the option of scheduling face-to-face meetings during the release of a new system. The goal is to provide 24/7 coverage and quick responses to issues. Which of the following strategies is being applied?

Options

  • ARisk acceptance
  • BRisk avoidance
  • CRisk transference
  • DRisk mitigation

Unlock PK0-004 to see the answer