A program manager asks for a visual representation of tasks, including the start and end dates. Which of the following tools should the project manager provide?

The correct answer is B. Gantt chart. A Gantt chart is a bar chart that provides a visual view of project tasks scheduled over time.

Tools and documentation

Question

A program manager asks for a visual representation of tasks, including the start and end dates. Which of the following tools should the project manager provide?

Options

  • ARun chart
  • BGantt chart
  • CProcess diagram
  • DHistogram

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    96% (26)

Explanation

A Gantt chart is a bar chart that provides a visual view of project tasks scheduled over time.