A program manager asks for a visual representation of tasks, including the start and end dates. Which of the following tools should the project manager provide?
The correct answer is B. Gantt chart. A Gantt chart is a bar chart that provides a visual view of project tasks scheduled over time.
Tools and documentation
Question
A program manager asks for a visual representation of tasks, including the start and end dates. Which of the following tools should the project manager provide?
Options
- ARun chart
- BGantt chart
- CProcess diagram
- DHistogram
How the community answered
(27 responses)- A4% (1)
- B96% (26)
Explanation
A Gantt chart is a bar chart that provides a visual view of project tasks scheduled over time.