Task A has a duration of 2 days and is a predecessor of task B, which has a duration of 3 days and is a predecessor of task C. Task C has a duration of 4 days. Task D has a start-to-start…

The correct answer is A. -9 days. The question asks to calculate the lead time for Task D based on its duration and a start-to-start dependency with Task A, such that both tasks conclude simultaneously.

Tools and documentation

Question

Task A has a duration of 2 days and is a predecessor of task B, which has a duration of 3 days and is a predecessor of task C. Task C has a duration of 4 days. Task D has a start-to-start relationship with task A and a duration of 11 days. Which of the following is the lag time for task D?

Options

  • A-9 days
  • B-2 days
  • C0 days
  • D2 days
  • E9 days

How the community answered

(36 responses)
  • A
    61% (22)
  • B
    3% (1)
  • C
    11% (4)
  • D
    6% (2)
  • E
    19% (7)

Why each option

The question asks to calculate the lead time for Task D based on its duration and a start-to-start dependency with Task A, such that both tasks conclude simultaneously.

A-9 daysCorrect

To have Task D finish at the same time as Task A, given Task A's duration of 2 days and Task D's duration of 11 days, Task D must start 9 days earlier than Task A. This is calculated as (Task A duration) - (Task D duration) = 2 - 11 = -9 days lag (lead time).

B-2 days

A -2 day lag would mean Task D starts 2 days before Task A, resulting in Task D finishing on day 9, not aligning with Task A's finish.

C0 days

A 0 day lag means Task D starts at the same time as Task A, causing Task D to finish 9 days after Task A.

D2 days

A 2 day lag means Task D starts 2 days after Task A, further extending Task D's finish beyond Task A's.

E9 days

A 9 day lag means Task D starts 9 days after Task A, which would significantly delay Task D's completion relative to Task A.

Concept tested: Project scheduling, lead/lag calculation

Topics

#lag time#task dependencies#critical path#schedule calculation