PK0-004 · Question #897
Since the CCB authorized proceeding with a formal change request, the project manager and team have been working to implement the change into production. Which of the following activities should the…
The correct answer is D. Communicate the implemented change. The formal change management sequence is: (1) evaluate the impact of the change, (2) submit a change request, (3) obtain change approval from the CCB, (4) implement the change, and finally (5) communicate the implemented change to stakeholders. Since the CCB has already…
Question
Since the CCB authorized proceeding with a formal change request, the project manager and team have been working to implement the change into production. Which of the following activities should the project manager do LAST?
Options
- AEvaluate the impact of the change.
- BSubmit a change request.
- CObtain change approval
- DCommunicate the implemented change
How the community answered
(38 responses)- A8% (3)
- B16% (6)
- C3% (1)
- D74% (28)
Explanation
The formal change management sequence is: (1) evaluate the impact of the change, (2) submit a change request, (3) obtain change approval from the CCB, (4) implement the change, and finally (5) communicate the implemented change to stakeholders. Since the CCB has already approved and implementation is underway, communicating the completed change is the final step. The other options - evaluate (A), submit (B), and obtain approval (C) - all precede implementation.