PK0-004 · Question #857
PK0-004 Question #857: Real Exam Question with Answer & Explanation
The correct answer is C: Network diagram. A network diagram is the deliverable produced when sequencing project activities derived from the WBS, showing logical dependencies and order. It is a prerequisite to developing the Gantt chart or project timeline.
Question
During the planning phase, a scheduler uses a WBS as a reference to create a list of activities. The next step of the process is to provide a sequence for all the activities. With which of the following deliverables is the scheduler working?
Options
- AWBS dictionary
- BProject timeline
- CNetwork diagram
- DGantt chart
Explanation
A network diagram is the deliverable produced when sequencing project activities derived from the WBS, showing logical dependencies and order. It is a prerequisite to developing the Gantt chart or project timeline.
Common mistakes.
- A. The WBS dictionary provides detailed definitions and attributes for each WBS element and is used as an input to activity definition, not as the result of sequencing activities.
- B. A project timeline is a high-level summary representation of the schedule and is produced after activity sequencing and duration estimating have already been completed.
- D. A Gantt chart is a time-phased bar chart used to display the finalized project schedule and can only be created after activity sequencing and duration estimation are complete.
Concept tested. Network diagram creation and activity sequencing process
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok