PK0-004 · Question #856

A project with a fixed budget is behind schedule. Immediately after the project due date, resources are allocated to other high-priority projects. Which of the following should the project manager…

The correct answer is B. Obtain resources from a third-party vendor. The project with a fixed budget needs to be completed on time to avoid any financial constraints. On allocation of resources to other high priority projects, the project manager can obtain resources from a third party vendor.

Project management concepts

Question

A project with a fixed budget is behind schedule. Immediately after the project due date, resources are allocated to other high-priority projects. Which of the following should the project manager do to complete this project?

Options

  • ARequest an increase in funding from the project sponsor
  • BObtain resources from a third-party vendor.
  • CCancel a project that is scheduled to start after this project.
  • DNegotiate the removal of selected deliverables.

How the community answered

(23 responses)
  • A
    26% (6)
  • B
    57% (13)
  • C
    4% (1)
  • D
    13% (3)

Explanation

The project with a fixed budget needs to be completed on time to avoid any financial constraints. On allocation of resources to other high priority projects, the project manager can obtain resources from a third party vendor.

Topics

#fixed budget#resource constraints#schedule recovery#vendor management

Community Discussion

No community discussion yet for this question.