PK0-004 · Question #856
A project with a fixed budget is behind schedule. Immediately after the project due date, resources are allocated to other high-priority projects. Which of the following should the project manager…
The correct answer is B. Obtain resources from a third-party vendor. The project with a fixed budget needs to be completed on time to avoid any financial constraints. On allocation of resources to other high priority projects, the project manager can obtain resources from a third party vendor.
Question
A project with a fixed budget is behind schedule. Immediately after the project due date, resources are allocated to other high-priority projects. Which of the following should the project manager do to complete this project?
Options
- ARequest an increase in funding from the project sponsor
- BObtain resources from a third-party vendor.
- CCancel a project that is scheduled to start after this project.
- DNegotiate the removal of selected deliverables.
How the community answered
(23 responses)- A26% (6)
- B57% (13)
- C4% (1)
- D13% (3)
Explanation
The project with a fixed budget needs to be completed on time to avoid any financial constraints. On allocation of resources to other high priority projects, the project manager can obtain resources from a third party vendor.
Topics
Community Discussion
No community discussion yet for this question.