PK0-004 · Question #875
A project team is ready to start working on a project; however, the project manager says the work needs to be planned first. Which of the following is MOST likely to be produced during the first…
The correct answer is A. Gantt chart. The Gantt chart is the central, overarching planning artifact because it visualizes the entire project schedule - tasks, durations, dependencies, and milestones. It is the primary deliverable that management and stakeholders expect from an initial planning workshop, as it…
Question
A project team is ready to start working on a project; however, the project manager says the work needs to be planned first. Which of the following is MOST likely to be produced during the first planning workshop?
Options
- AGantt chart
- BRACI
- CWBS
- DRisk register
How the community answered
(41 responses)- A93% (38)
- B5% (2)
- C2% (1)
Explanation
The Gantt chart is the central, overarching planning artifact because it visualizes the entire project schedule - tasks, durations, dependencies, and milestones. It is the primary deliverable that management and stakeholders expect from an initial planning workshop, as it communicates when work will happen. The other artifacts feed into or support it but are often developed in subsequent or parallel planning activities.