nerdexam
CompTIA

PK0-004 · Question #875

A project team is ready to start working on a project; however, the project manager says the work needs to be planned first. Which of the following is MOST likely to be produced during the first…

The correct answer is A. Gantt chart. The Gantt chart is the central, overarching planning artifact because it visualizes the entire project schedule - tasks, durations, dependencies, and milestones. It is the primary deliverable that management and stakeholders expect from an initial planning workshop, as it…

Project life cycle phases

Question

A project team is ready to start working on a project; however, the project manager says the work needs to be planned first. Which of the following is MOST likely to be produced during the first planning workshop?

Options

  • AGantt chart
  • BRACI
  • CWBS
  • DRisk register

How the community answered

(41 responses)
  • A
    93% (38)
  • B
    5% (2)
  • C
    2% (1)

Explanation

The Gantt chart is the central, overarching planning artifact because it visualizes the entire project schedule - tasks, durations, dependencies, and milestones. It is the primary deliverable that management and stakeholders expect from an initial planning workshop, as it communicates when work will happen. The other artifacts feed into or support it but are often developed in subsequent or parallel planning activities.

Topics

#planning phase#Gantt chart#project schedule#planning workshop

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice