PK0-004 · Question #890
Which of the following activities should be done by a resource other than the PMO?
The correct answer is D. Creating a project charter. The PMO (Project Management Office) is responsible for governance functions: providing project control, coordinating resources across projects, and setting standards and practices. However, creating a project charter is the responsibility of the project sponsor (who authorizes…
Question
Which of the following activities should be done by a resource other than the PMO?
Options
- AProviding project control
- BCoordinating resources between projects
- CSetting standards and practices
- DCreating a project charter
How the community answered
(44 responses)- A14% (6)
- B2% (1)
- C7% (3)
- D77% (34)
Explanation
The PMO (Project Management Office) is responsible for governance functions: providing project control, coordinating resources across projects, and setting standards and practices. However, creating a project charter is the responsibility of the project sponsor (who authorizes the project) and/or the project manager (who may draft it). The PMO may provide templates or guidance for the charter, but the actual creation and authorization is done outside the PMO. This distinction reflects the PMO's governance and support role versus the execution role of the project sponsor and manager.