nerdexam
CompTIA

PK0-004 · Question #890

Which of the following activities should be done by a resource other than the PMO?

The correct answer is D. Creating a project charter. The PMO (Project Management Office) is responsible for governance functions: providing project control, coordinating resources across projects, and setting standards and practices. However, creating a project charter is the responsibility of the project sponsor (who authorizes…

Basics of IT and governance

Question

Which of the following activities should be done by a resource other than the PMO?

Options

  • AProviding project control
  • BCoordinating resources between projects
  • CSetting standards and practices
  • DCreating a project charter

How the community answered

(44 responses)
  • A
    14% (6)
  • B
    2% (1)
  • C
    7% (3)
  • D
    77% (34)

Explanation

The PMO (Project Management Office) is responsible for governance functions: providing project control, coordinating resources across projects, and setting standards and practices. However, creating a project charter is the responsibility of the project sponsor (who authorizes the project) and/or the project manager (who may draft it). The PMO may provide templates or guidance for the charter, but the actual creation and authorization is done outside the PMO. This distinction reflects the PMO's governance and support role versus the execution role of the project sponsor and manager.

Topics

#PMO responsibilities#project charter#organizational governance#project manager roles

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice