PK0-004 · Question #869
Two team members are discussing the lessons learned from the last testing release. Many quality defects were not reported, and the progress report is not accurate. Which of the following…
The correct answer is C. Closing/gathering lessons learned. In a lessons learned meeting, a team comes together to review a project, milestone, or sprint with other team members to discover what did and didn't go well.
Project life cycle phases
Question
Two team members are discussing the lessons learned from the last testing release. Many quality defects were not reported, and the progress report is not accurate. Which of the following phases/activities are being executed?
Options
- APlanning/governance
- BMonitoring/performance measuring
- CClosing/gathering lessons learned
- DExecuting/performing project team
How the community answered
(38 responses)- A3% (1)
- B3% (1)
- C87% (33)
- D8% (3)
Explanation
In a lessons learned meeting, a team comes together to review a project, milestone, or sprint with other team members to discover what did and didn't go well.
Topics
#lessons learned#closing phase#quality defects#performance reporting