nerdexam
ExamsPK0-004Questions#899
CompTIA

PK0-004 · Question #899

PK0-004 Question #899: Real Exam Question with Answer & Explanation

The correct answer is A: Risk mitigation. Risk mitigation involves taking proactive action to reduce the probability or impact of a negative risk event. Here, the team cannot eliminate the risk (avoidance) or transfer it, and has not simply accepted it passively. Instead, they are actively applying a workaround - a concr

Question

A regulatory project is behind schedule, and the project manager informs the steering committee that more resources are needed to complete the automation requirements on time. However, the funding request was rejected. To be in compliance, the project team performs a physical workaround to attempt to complete the project on time. Which of the following is this an example of?

Options

  • ARisk mitigation
  • BRisk acceptance
  • CRisk exploitation
  • DRisk avoidance

Explanation

Risk mitigation involves taking proactive action to reduce the probability or impact of a negative risk event. Here, the team cannot eliminate the risk (avoidance) or transfer it, and has not simply accepted it passively. Instead, they are actively applying a workaround - a concrete action - to reduce the impact of the schedule risk and maintain compliance. Exploitation (C) applies to opportunities, not threats. Acceptance (B) would mean doing nothing and absorbing the consequence.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice
A regulatory project is behind schedule, and the project manager... | PK0-004 Q#899 Answer | NerdExam