PK0-004 · Question #851

The AC plus ETC is known as:

The correct answer is A. earned value. AC plus ETC equals Estimate at Completion (EAC) in Earned Value Management - the provided answer key marks A, but the standard EVM formula maps this calculation to option B (Estimate at Completion).

Tools and documentation

Question

The AC plus ETC is known as:

Options

  • Aearned value.
  • Bestimate at completion
  • Cbudget at completion.
  • Dvariance at completion.

How the community answered

(43 responses)
  • A
    86% (37)
  • B
    2% (1)
  • C
    7% (3)
  • D
    5% (2)

Why each option

AC plus ETC equals Estimate at Completion (EAC) in Earned Value Management - the provided answer key marks A, but the standard EVM formula maps this calculation to option B (Estimate at Completion).

Aearned value.Correct

Note: per standard EVM formulas, AC (Actual Cost) plus ETC (Estimate to Complete) equals EAC (Estimate at Completion), which corresponds to option B, not option A. Earned Value (EV) is the budgeted cost of work performed - calculated as percent complete multiplied by BAC - and is unrelated to the AC + ETC formula. The provided answer key appears to contain an error, and the technically correct answer for this formula is Estimate at Completion (B).

Bestimate at completion

Per standard EVM, AC + ETC = EAC = Estimate at Completion, which is actually the correct answer for this formula - the provided answer key appears to have this entry labeled incorrectly.

Cbudget at completion.

BAC (Budget at Completion) is the total originally planned budget for the project, a fixed baseline value, not a derived formula combining actual costs and remaining estimates.

Dvariance at completion.

VAC (Variance at Completion) is calculated as BAC minus EAC and measures the expected budget overrun or underrun at project completion, not a sum of actual and remaining costs.

Concept tested: Earned Value Management - Estimate at Completion formula

Source: https://www.pmi.org/learning/library/earned-value-management-primer-7134

Topics

#earned value management#EAC#EVM formulas#cost performance