Agate review also is considered:

The correct answer is C. a checkpoint to review schedule changes. A phase-gate review, also known as a governance-gate review, is a check point review of project deliverables and performance that occurs at the end of each phase of a project where a management review or sign-off may be required

Project life cycle phases

Question

Agate review also is considered:

Options

  • Aa method to make changes to resources.
  • Ban update to an incident response plan
  • Ca checkpoint to review schedule changes
  • Da type of audit occurring during the project.

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    86% (32)
  • D
    8% (3)

Explanation

A phase-gate review, also known as a governance-gate review, is a check point review of project deliverables and performance that occurs at the end of each phase of a project where a management review or sign-off may be required

Topics

#gate review#phase gate#project audit#lifecycle checkpoint