nerdexam
ExamsPK0-004Questions#866
CompTIA

PK0-004 · Question #866

PK0-004 Question #866: Real Exam Question with Answer & Explanation

The correct answer is C: RACI chart. RACI chart (Responsible, Accountable, Consulted, and Informed) This chart is a type of Responsibility Assignment Matrix (RAM) that helps detect the level of responsibility for each project team member.

Question

A project stakeholder is disappointed the team was not included in some key decisions. This resulted in extra discussions and rework. Which of the following documents should the project manager review and update to resolve this situation?

Options

  • ACollaboration site
  • BDashboard
  • CRACI chart
  • DWiki page

Explanation

RACI chart (Responsible, Accountable, Consulted, and Informed) This chart is a type of Responsibility Assignment Matrix (RAM) that helps detect the level of responsibility for each project team member.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice