A project stakeholder is disappointed the team was not included in some key decisions. This resulted in extra discussions and rework. Which of the following documents should the project manager…
The correct answer is C. RACI chart. RACI chart (Responsible, Accountable, Consulted, and Informed) This chart is a type of Responsibility Assignment Matrix (RAM) that helps detect the level of responsibility for each project team member.
Tools and documentation
Question
A project stakeholder is disappointed the team was not included in some key decisions. This resulted in extra discussions and rework. Which of the following documents should the project manager review and update to resolve this situation?
Options
- ACollaboration site
- BDashboard
- CRACI chart
- DWiki page
How the community answered
(26 responses)- A4% (1)
- C92% (24)
- D4% (1)
Explanation
RACI chart (Responsible, Accountable, Consulted, and Informed) This chart is a type of Responsibility Assignment Matrix (RAM) that helps detect the level of responsibility for each project team member.
Topics
#RACI chart#stakeholder management#roles and responsibilities#decision authority