A new project manager was hired to help transition projects from the waterfall style to an approach based on iterative refinement. This method has never been used by the organization and would mark…

The correct answer is C. Project management office. A project management office (PMO) is a group or department that defines, maintains and ensures project management standards across an organization.

Project management concepts

Question

A new project manager was hired to help transition projects from the waterfall style to an approach based on iterative refinement. This method has never been used by the organization and would mark a significant change in approach from previous projects. Which of the following should the project manager contact for guidance and approval for the new methodology?

Options

  • AProject coordinator
  • BProject team
  • CProject management office
  • DProject sponsor

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    13% (5)
  • C
    78% (31)
  • D
    8% (3)

Explanation

A project management office (PMO) is a group or department that defines, maintains and ensures project management standards across an organization.

Topics

#PMO#Agile transformation#methodology governance#organizational change