- Question #636Adaptive Planning
During a mature agile team's planning meeting, a team member proposes a new framework that would considerably reduce implementation time. However, the team lacks the confidence to...
Agile SpikesUncertainty ReductionExperimentationTeam Confidence - Question #637Stakeholder Engagement
An agile practitioner wants to ensure that stakeholders have current information about a project's progress. What should the agile practitioner do?
Stakeholder CommunicationInformation RadiatorsProject TransparencyProgress Visibility - Question #638Team Performance
A product owner, new to the role, is very enthusiastic about an agile project with an energetic team. What should be done first to ensure successful delivery of the product?
Team CharterWorking AgreementsTeam CollaborationProduct Owner Integration - Question #639Team Performance
Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retrospective. What should...
Retrospective facilitationPsychological safetyGround rulesTeam conflict - Question #640Adaptive Planning
Two similar stories, A and B, are estimated at 3 story points. Story C, is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took...
Story Point EstimationEstimation CalibrationAdaptive PlanningContinuous Learning - Question #641Continuous Improvement
During a current sprint, a team member asks permission from the scrum master to investigate an alternative design approach. What should the scrum master do?
Scrum Master RoleContinuous ImprovementExperimentation/SpikesSelf-organizing Teams - Question #642Problem Detection and Resolution
An agile team member identifies a potential problem within the project team. How should the team's coach react?
Agile Coach RoleValue Stream MappingProcess ImprovementProblem Solving - Question #644Value-driven Delivery
A customer and a product delivery team meet to discuss a product's attributes, goals, expectations, hypothesis, and high-level needs. What is a benefit of this meeting?
Product VisionValue UnderstandingCustomer CollaborationTeam Empowerment - Question #645Agile Principles and Mindset
While reviewing the sprint burn down during a stand up, the scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (...
Scrum RolesSelf-organizationSprint ManagementBacklog Prioritization - Question #647Stakeholder Engagement
The agile team disagrees with the business stakeholders on completing some epics. What could help eliminate misunderstandings?
Sprint DemosStakeholder FeedbackMisunderstanding ResolutionAgile Collaboration - Question #648Team Performance
During a project meeting, a team is faced with a difficult decision. After discussion and deliberation, the project leader makes the final decision and ends the discussion. This ca...
Agile LeadershipDecision MakingTeam CollaborationTeam Dynamics - Question #649Team Performance
A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge. What should the agile...
Distributed TeamsCollaboration ToolsTeam CommunicationAgile Practices - Question #650Continuous Improvement
During a retrospective meeting, a team develops a large list of initiatives. All will have a positive impact and improve team performance. What should the agile coach do next?
RetrospectiveContinuous ImprovementAgile Coach RolePrioritization - Question #651Adaptive Planning
The team is refining user stories during the backlog grooming session and confused on the acceptance criteria and level of details. What should the agile practitioner do?
User StoriesAcceptance CriteriaBacklog RefinementTest Scenarios - Question #652Stakeholder Engagement
How should an agile project leader interact with the product owner?
Product OwnerAgile ceremoniesStakeholder communicationFeedback mechanisms - Question #653Team Performance
A company is moving into a new space and is determining the best configuration for offices. The management team is also considering moving to an agile process. What advice should a...
Office configurationCo-locationTeam collaborationAgile environment - Question #654Continuous Improvement
During planning sessions, an agile practitioner notices that some team members do not share common ideas. What should the agile practitioner do?
Team CollaborationAgile FacilitationProcess AdaptationPlanning Sessions - Question #655Value-driven Delivery
A product owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog. What should the product owner do nex...
Value deliveryProduct Owner roleBacklog prioritizationEarly value realization - Question #656Problem Detection and Resolution
A project team identifies a number of technical challenges with features in the next sprint. What should they do?
Problem-solvingSelf-organizing teamsTechnical challengesTeam responsibility - Question #657Value-driven Delivery
debt. What should the team do?
Technical Debt ManagementProduct Backlog PrioritizationProduct Owner RoleValue Maximization - Question #658Stakeholder Engagement
How can an agile team working on a new product ensure alignment with external stakeholders?
Story mappingStakeholder engagementProduct visionPrioritization - Question #659Stakeholder Engagement
A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these require...
Scrum Master roleInformation radiatorsTransparencyStakeholder communication - Question #660Stakeholder Engagement
Team A is working on the second sprint of a product release. Team B, which is an interdependent team located on the same floor, requires extensive and frequent information to compl...
Information SharingInterdependent TeamsStakeholder CommunicationTransparency - Question #661Stakeholder Engagement
What should an agile practitioner do to ensure that the end product meets business requirements?
Stakeholder engagementProduct validationIteration reviewBusiness requirements - Question #662Stakeholder Engagement
A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time. What should the product owner do?
Product Owner RoleStakeholder CommunicationBacklog PrioritizationValue Management - Question #663Adaptive Planning
Based on the backlog metrics in the chart, what can explain the jump in points at the end of iteration 4?
Backlog ManagementStory PointsEstimationAgile Metrics - Question #664Adaptive Planning
An agile team is preparing a release plan for a project. What information will the team need to complete this plan?
Release PlanningIteration VelocityAgile Planning - Question #665Value-driven Delivery
When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?
PrioritizationRisk-value matrixValue optimizationFeature selection - Question #666Value-driven Delivery
During a review session, an agile team presented done requirements to a group of stakeholders. Stakeholder feedback indicated that the done requirements failed to meet the most pre...
Backlog PrioritizationValue DeliveryStakeholder FeedbackIteration Planning - Question #667Problem Detection and Resolution
Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected. What should the p...
Product Owner RoleProblem ResolutionRisk ResponseStrategic Decision Making - Question #668Value-driven Delivery
A company is considering developing a new, complex application that will require a large initial investment. However, if successful, the profit potential is high. When preparing an...
Minimally Marketable Features (MMFs)Value-driven developmentRisk mitigationStakeholder confidence - Question #669Adaptive Planning
Midway through a sprint, a scrum team member advises the team of a new requirement that may change the initial scope. What should the team do?
Product BacklogScrum FrameworkRequirement ManagementAdaptive Planning - Question #670Stakeholder Engagement
How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?
Stakeholder EngagementAgile PlanningRoadmapWorkshops - Question #671Value-driven Delivery
Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of...
Product Owner roleValue maximizationWaste reductionAdaptive scope - Question #672Team Performance
A development team and product owner disagree on a user story in the product backlog. What should the agile practitioner do?
FacilitationConflict ResolutionTeam CollaborationAgile Coaching - Question #673Team Performance
What should a Scrum Master do when one team member falls behind in their tasks?
Scrum Master RoleTeam Self-OrganizationImpediment ResolutionTeam Collaboration - Question #674Problem Detection and Resolution
A member of the development team is working on a prioritized non-functional requirement involving integrating with a 3rd party system. This integration has not been done before on...
Agile SpikesNon-functional RequirementsRisk ManagementTechnical Exploration - Question #675Problem Detection and Resolution
A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its...
Root cause analysisFishbone diagramProcess delaysProblem solving - Question #676Agile Principles and Mindset
During sprint planning, team members have differing opinions on a feature that delivers business value but fails to provide a long-term solution for the customer. How should the te...
Sprint PlanningTeam ConflictAgile ValuesDecision Making - Question #677Team Performance
During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories. What should the scrum master do?
Scrum Master RoleImpediment RemovalTeam CollaborationSelf-organizing Teams - Question #678Stakeholder Engagement
During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision. The stakeholder asks for detailed requirements, de...
Stakeholder managementExpectation settingProgressive elaborationAgile planning - Question #679Adaptive Planning
As user stories are developed, what should be done to record and update acceptance criteria?
User StoriesAcceptance CriteriaRequirements ManagementAgile Artifacts - Question #680Value-driven Delivery
A team is creating a highly marketed, time-sensitive product. The agile coach is concerned that anything other than exceptional quality will result in bad publicity for the company...
Iteration ReviewProduct DemosAgile Quality AssuranceStakeholder Feedback - Question #681Team Performance
An agile team has only one database administrator with the necessary knowledge of database- related tasks. The project manager identifies the risk that if this person leaves, team...
Knowledge sharingCross-trainingRisk mitigationTeam resilience - Question #682Adaptive Planning
During a backlog refinement meeting, a senior team member raises a concern about an epic sizing that requires the use of a new interface for a vendor product. The product owner ack...
Spike storyTechnical uncertaintyRisk mitigationBacklog refinement - Question #683Stakeholder Engagement
A product that recently went to market is receiving a great deal of attention from upper management who expresses interest by directly emailing and calling the developer team. The...
Scrum Master responsibilitiesProduct Owner responsibilitiesStakeholder communicationTeam impediments - Question #684Stakeholder Engagement
An executive requests information regarding a sprint status. What action should the product owner take?
Information RadiatorStakeholder CommunicationTransparencyProduct Owner Role - Question #685Stakeholder Engagement
An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of...
Requirements ElaborationStakeholder CollaborationBacklog RefinementAgile Workshops - Question #686Agile Principles and Mindset
A new CIO advocates an agile framework for new IT projects, but the team has reservations. How should the CIO ensure that the team will be aligned with this?
Agile AdoptionOrganizational ChangeTeam Buy-inEmpirical Process - Question #687Problem Detection and Resolution
An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unab...
Velocity managementRetrospectiveCorrective actionAgile forecasting