PMI-ACP · Question #661

What should an agile practitioner do to ensure that the end product meets business requirements?

The correct answer is D. Confirm managers and stakeholders are invited to product review meetings. Sprint review (product review) meetings are the primary ceremony where the team demonstrates working software to gather stakeholder feedback and confirm alignment with business goals. Ensuring that managers and stakeholders are present closes the feedback loop and validates…

Submitted by jordan8· Apr 18, 2026Stakeholder Engagement

Question

What should an agile practitioner do to ensure that the end product meets business requirements?

Options

  • AInvite the team to iteration review meetings
  • BObtain agreement from the product owner on business requirements
  • CRequest that regular reports are sent to stakeholders
  • DConfirm managers and stakeholders are invited to product review meetings

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    5% (2)
  • D
    90% (35)

Explanation

Sprint review (product review) meetings are the primary ceremony where the team demonstrates working software to gather stakeholder feedback and confirm alignment with business goals. Ensuring that managers and stakeholders are present closes the feedback loop and validates that the product is being built correctly. Inviting only the team (A) omits the business perspective. Obtaining agreement solely from the product owner (B) narrows the validation to one person. Regular status reports (C) describe progress but don't facilitate the interactive feedback needed to confirm the product meets business requirements.

Topics

#Stakeholder engagement#Product validation#Iteration review#Business requirements