nerdexam
PMIPMI

PMI-ACP · Question #743

PMI-ACP Question #743: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #743. The question stem and answer options stay visible for context.

Submitted by yuriko_h· Apr 18, 2026Stakeholder Engagement

Question

After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met. If the problem were an issue of requirement elicitation rather than delivery, what should have been done to avoid this situation?

Options

  • AStakeholders should have regularly been engaged to obtain feedback and reduce the functionality
  • BThe team should have used the lean principle of delay, so that actual facts could be considered
  • CInterdependent teams should have been engaged using a collaborative approach to identify and
  • DAn owner should have been identified to obtain timely stakeholder feedback.

Unlock PMI-ACP to see the answer

You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder feedback#Requirement elicitation#Business value#Continuous engagement
Full PMI-ACP PracticeBrowse All PMI-ACP Questions