PMI-ACP · Question #742

During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good. What…

The correct answer is D. Encourage the team to try the ideas, even if failure may be the outcome. Learning takes place by experimenting, delivering small increments of value, and getting feedback on what has been accomplished thus far.

Submitted by valeria.br· Apr 18, 2026Continuous Improvement

Question

During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good. What should the agile team lead do?

Options

  • ARequire the team to try only those ideas that will ensure success.
  • BAllow the team to try ideas, but remind them that results will be reviewed by high-ranking
  • CAssociate idea successes and failures with the team's incentive plan to ensure accountability.
  • DEncourage the team to try the ideas, even if failure may be the outcome.

How the community answered

(32 responses)
  • A
    16% (5)
  • B
    3% (1)
  • C
    6% (2)
  • D
    75% (24)

Explanation

Learning takes place by experimenting, delivering small increments of value, and getting feedback on what has been accomplished thus far.