nerdexam
PMI

PMI-ACP · Question #96

In an Agile approach, at which meeting does a team examine the effectiveness of risk responses by conducting a risk audit?

The correct answer is C. Sprint Retrospective. The Sprint Retrospective is the dedicated Agile ceremony for inspecting the team's processes, practices, and responses - including how well risk mitigation strategies worked during the sprint. It is the appropriate forum for a risk audit because the team reflects on what happened

Submitted by tunde_lagos· Apr 18, 2026Continuous Improvement

Question

In an Agile approach, at which meeting does a team examine the effectiveness of risk responses by conducting a risk audit?

Options

  • ARelease planning
  • BSprint planning
  • CSprint Retrospective
  • DDaily Scrum

How the community answered

(48 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    88% (42)
  • D
    6% (3)

Explanation

The Sprint Retrospective is the dedicated Agile ceremony for inspecting the team's processes, practices, and responses - including how well risk mitigation strategies worked during the sprint. It is the appropriate forum for a risk audit because the team reflects on what happened and improves. Release planning (A) focuses on roadmap scope. Sprint Planning (B) focuses on upcoming work. The Daily Scrum (D) is a short synchronization meeting focused on the next 24 hours, not retrospective process evaluation.

Topics

#Sprint Retrospective#Risk Management#Continuous Improvement#Agile Events

Community Discussion

No community discussion yet for this question.

Full PMI-ACP Practice