The correct answer is C: Sprint Retrospective. The Sprint Retrospective is the dedicated Agile ceremony for inspecting the team's processes, practices, and responses — including how well risk mitigation strategies worked during the sprint. It is the appropriate forum for a risk audit because the team reflects on what happen
Question
In an Agile approach, at which meeting does a team examine the effectiveness of risk responses by conducting a risk audit?
Options
- ARelease planning
- BSprint planning
- CSprint Retrospective
- DDaily Scrum
Explanation
The Sprint Retrospective is the dedicated Agile ceremony for inspecting the team's processes, practices, and responses — including how well risk mitigation strategies worked during the sprint. It is the appropriate forum for a risk audit because the team reflects on what happened and improves. Release planning (A) focuses on roadmap scope. Sprint Planning (B) focuses on upcoming work. The Daily Scrum (D) is a short synchronization meeting focused on the next 24 hours, not retrospective process evaluation.
Topics
Community Discussion
No community discussion yet for this question.