PMI-ACP · Question #397
PMI-ACP Question #397: Real Exam Question with Answer & Explanation
The correct answer is C: Sprint Retrospective. Triple Nickels is a structured brainstorming technique commonly used in Sprint Retrospectives. Each participant silently writes ideas on paper for 5 minutes, then passes their paper to the next person, who reads what was written and adds new ideas for another 5 minutes. This cont
Question
Triple Nickels is a technique used in what kind of meeting?
Options
- ASprint Planning
- BDaily Scrum
- CSprint Retrospective
- DXP Planning Game
Explanation
Triple Nickels is a structured brainstorming technique commonly used in Sprint Retrospectives. Each participant silently writes ideas on paper for 5 minutes, then passes their paper to the next person, who reads what was written and adds new ideas for another 5 minutes. This continues around the group. The technique encourages every voice, prevents groupthink, and surfaces a wide variety of improvement ideas—making it well-suited for the retrospective's goal of continuous team improvement.
Topics
Community Discussion
No community discussion yet for this question.