Which of the following is a list of capabilities, features, and stories that the Product Owner has identified?

The correct answer is D. Backlog. The Product Backlog is the single, ordered list of all work items - epics, features, user stories, and tasks - that the Product Owner maintains and prioritizes for the development team. It is the authoritative source of requirements in Scrum. A burndown chart (A) tracks…

Submitted by salim_om· Apr 18, 2026Value-driven Delivery

Question

Which of the following is a list of capabilities, features, and stories that the Product Owner has identified?

Options

  • ABurndown chart
  • BStory card
  • CVision document
  • DBacklog

How the community answered

(64 responses)
  • A
    3% (2)
  • B
    2% (1)
  • C
    2% (1)
  • D
    94% (60)

Explanation

The Product Backlog is the single, ordered list of all work items - epics, features, user stories, and tasks - that the Product Owner maintains and prioritizes for the development team. It is the authoritative source of requirements in Scrum. A burndown chart (A) tracks remaining work over time. A story card (B) represents a single user story. A vision document (C) describes the high-level product goals but is not an itemized list of work.

Topics

#Product Backlog#Product Owner#Agile artifacts#Requirements management