PMI-ACP · Question #596
PMI-ACP Question #596: Real Exam Question with Answer & Explanation
The correct answer is C: It represents unrealized value. Work in progress (WIP) refers to work that has been started but not yet completed and delivered. Until a work item is done and in the customer's hands, it delivers zero value — it is unrealized value sitting in the system. Reducing WIP helps teams focus on finishing items befor
Question
Why should a project team reduce the work in progress?
Options
- AIt indicates poor project quality
- BIt represents team members' utilization
- CIt represents unrealized value
- DIt shows that the project is behind schedule
Explanation
Work in progress (WIP) refers to work that has been started but not yet completed and delivered. Until a work item is done and in the customer's hands, it delivers zero value — it is unrealized value sitting in the system. Reducing WIP helps teams focus on finishing items before starting new ones, which increases flow efficiency and delivers value sooner. WIP is not an indicator of quality (A), it does not represent utilization (B) — that is a capacity concept — and high WIP does not inherently mean the project is behind schedule (D).
Topics
Community Discussion
No community discussion yet for this question.