PMI-ACP · Question #56

To ensure the success of our project, in what order should we execute the work, taking into account the necessary dependencies and risk mitigation tasks?

The correct answer is B. The order specified by the business representatives. Business representatives (e.g., the Product Owner or business stakeholders) determine the priority and order of work because they understand the business value, ROI, and risk tolerance of each item. They sequence the backlog considering dependencies and risk mitigation to maximiz

Submitted by renata2k· Apr 18, 2026Value-driven Delivery

Question

To ensure the success of our project, in what order should we execute the work, taking into account the necessary dependencies and risk mitigation tasks?

Options

  • AThe order specified by the project management office (PMO.
  • BThe order specified by the business representatives
  • CThe order specified by the project team
  • DThe order specified by the project architect

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    89% (34)
  • C
    3% (1)
  • D
    5% (2)

Explanation

Business representatives (e.g., the Product Owner or business stakeholders) determine the priority and order of work because they understand the business value, ROI, and risk tolerance of each item. They sequence the backlog considering dependencies and risk mitigation to maximize value delivery. While the project team (C) influences estimates and feasibility, and the architect (D) may advise on technical sequencing, ultimate ordering authority rests with those accountable for business outcomes. The PMO (A) typically sets governance standards but does not dictate individual work sequencing.

Topics

#Prioritization#Business Value#Product Owner Role#Value-driven Delivery