In reference to Scrum, each sprint should produce:

The correct answer is A. An increment of potentially shippable product functionality.. A core Scrum principle is that every sprint must end with a 'Done' increment of potentially shippable product functionality. 'Potentially shippable' means the increment meets the team's Definition of Done and could be released to users at the Product Owner's discretion - even if

Submitted by omar99· Apr 18, 2026Value-driven Delivery

Question

In reference to Scrum, each sprint should produce:

Options

  • AAn increment of potentially shippable product functionality.
  • BAset of documented product requirements and specifications.
  • CArelease with testable and measurable functionality.
  • DAn increment of potentially testable product functionality.

How the community answered

(21 responses)
  • A
    95% (20)
  • C
    5% (1)

Explanation

A core Scrum principle is that every sprint must end with a 'Done' increment of potentially shippable product functionality. 'Potentially shippable' means the increment meets the team's Definition of Done and could be released to users at the Product Owner's discretion - even if the PO chooses not to. Option D is a common distractor; 'testable' alone is insufficient because the increment must also be releasable, not just testable. Option B describes a waterfall artifact. Option C conflates the sprint output with a formal release decision, which is the PO's call, not a sprint requirement.