The primary purpose of a Sprint Review is for the team to:

The correct answer is A. Demonstrate what was accomplished during the sprint. The Sprint Review is an inspection-and-adaptation event where the Scrum Team demonstrates completed work to stakeholders and collects feedback on the increment. Its primary purpose is to show what was accomplished. Option B describes the Sprint Retrospective, which focuses on…

Submitted by dimitri_ru· Apr 18, 2026Value-driven Delivery

Question

The primary purpose of a Sprint Review is for the team to:

Options

  • ADemonstrate what was accomplished during the sprint.
  • BDiscuss what went well, whatdidn't, and ways to improve.
  • CPrioritize and estimate stories planned for the next sprint.
  • DIndividually provide status updates on user stories in progress.

How the community answered

(27 responses)
  • A
    85% (23)
  • B
    4% (1)
  • C
    7% (2)
  • D
    4% (1)

Explanation

The Sprint Review is an inspection-and-adaptation event where the Scrum Team demonstrates completed work to stakeholders and collects feedback on the increment. Its primary purpose is to show what was accomplished. Option B describes the Sprint Retrospective, which focuses on the team's process and continuous improvement. Option C describes Sprint Planning. Option D (individual status updates) contradicts Agile's team-based, transparent approach and has no place in a Sprint Review.

Topics

#Sprint Review#Scrum Events#Increment Demonstration#Agile Ceremonies