Submitted by tunde_lagos· Apr 18, 2026Agile Principles and Mindset
Question
An agile team's client has been asked to expedite the delivery of the next release. By delivering one month early, the company can generate US$40,000 more than expected for the quarter. What should the agile team do?
Options
- AAdhere to the new deadline and immediately advise the client that the schedule has been
- BAdvise the client that it is best to continue as planned rather than introduce unforeseen risks by
- CSubmit a change request to the client with a 50% increase in charges due to the new potential
- DRequest additional resources to meet the expedited deadline and obtain training for the new
Unlock PMI-ACP to see the answer
You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Sustainable pace#Risk management#Stakeholder collaboration#Trade-off analysis