PMI-ACP · Question #482
PMI-ACP Question #482: Real Exam Question with Answer & Explanation
The correct answer is B: False. When multiple Scrum teams work on the same product, they must mutually agree on and share a single definition of Done for that product. This ensures all teams produce integrated, consistent increments. Individual teams may have additional internal quality standards, but a shared
Question
If there are multiple Scrum teams working on a product, each needs its own definition of Done.
Options
- ATrue
- BFalse
Explanation
When multiple Scrum teams work on the same product, they must mutually agree on and share a single definition of Done for that product. This ensures all teams produce integrated, consistent increments. Individual teams may have additional internal quality standards, but a shared baseline definition of Done is required to maintain coherent product quality across teams.
Topics
Community Discussion
No community discussion yet for this question.