PMI-ACP · Question #482

PMI-ACP Question #482: Real Exam Question with Answer & Explanation

The correct answer is B: False. When multiple Scrum teams work on the same product, they must mutually agree on and share a single definition of Done for that product. This ensures all teams produce integrated, consistent increments. Individual teams may have additional internal quality standards, but a shared

Submitted by neha2k· Apr 18, 2026Agile Principles and Mindset

Question

If there are multiple Scrum teams working on a product, each needs its own definition of Done.

Options

  • ATrue
  • BFalse

Explanation

When multiple Scrum teams work on the same product, they must mutually agree on and share a single definition of Done for that product. This ensures all teams produce integrated, consistent increments. Individual teams may have additional internal quality standards, but a shared baseline definition of Done is required to maintain coherent product quality across teams.

Topics

#Definition of Done#Scaled Scrum#Product Increment#Shared Understanding