PMI-ACP · Question #418
Which of the following is not an Agile methodology?
The correct answer is E. Program Evaluation Review Technique (PERT). PERT is a traditional, waterfall-era project management tool used to analyze and schedule tasks by estimating optimistic, pessimistic, and most-likely durations. It is not an Agile methodology. All other options - Scrum, FDD, XP, DSDM, Crystal Clear, RUP, and AgileUP - are recogn
Question
Which of the following is not an Agile methodology?
Options
- AScrum
- BFeature Driven Development (FDD)
- CExtreme Programming (XP)
- DDynamic Systems Development Method (DSDM)
- EProgram Evaluation Review Technique (PERT)
- FCrystal Clear
- GRational Unified Process (RUP)
- HAgile Unified Process (AgileUP)
How the community answered
(31 responses)- A3% (1)
- B6% (2)
- E87% (27)
- G3% (1)
Explanation
PERT is a traditional, waterfall-era project management tool used to analyze and schedule tasks by estimating optimistic, pessimistic, and most-likely durations. It is not an Agile methodology. All other options - Scrum, FDD, XP, DSDM, Crystal Clear, RUP, and AgileUP - are recognized Agile methodologies or Agile-aligned frameworks.
Topics
Community Discussion