Which of the following is not an Agile methodology?

The correct answer is E. Program Evaluation Review Technique (PERT). PERT is a traditional, waterfall-era project management tool used to analyze and schedule tasks by estimating optimistic, pessimistic, and most-likely durations. It is not an Agile methodology. All other options - Scrum, FDD, XP, DSDM, Crystal Clear, RUP, and AgileUP - are recogn

Submitted by andres_qro· Apr 18, 2026Agile Principles and Mindset

Question

Which of the following is not an Agile methodology?

Options

  • AScrum
  • BFeature Driven Development (FDD)
  • CExtreme Programming (XP)
  • DDynamic Systems Development Method (DSDM)
  • EProgram Evaluation Review Technique (PERT)
  • FCrystal Clear
  • GRational Unified Process (RUP)
  • HAgile Unified Process (AgileUP)

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    6% (2)
  • E
    87% (27)
  • G
    3% (1)

Explanation

PERT is a traditional, waterfall-era project management tool used to analyze and schedule tasks by estimating optimistic, pessimistic, and most-likely durations. It is not an Agile methodology. All other options - Scrum, FDD, XP, DSDM, Crystal Clear, RUP, and AgileUP - are recognized Agile methodologies or Agile-aligned frameworks.

Topics

#Agile methodologies#Agile frameworks#PERT#Methodology recognition