PMI-ACP · Question #526
PMI-ACP Question #526: Real Exam Question with Answer & Explanation
The correct answer is A: True. Every PMLC model — whether Linear (Waterfall), Incremental, Iterative, Adaptive, or Extreme — follows a defined sequence of phases such as Scoping, Planning, Launching, Monitoring & Controlling, and Closing. While the emphasis and iteration frequency differ across models, the
Question
Every Project Management Life Cycle (PMLC) has a sequence of processes that include these phases:
Options
- ATrue
- BFalse
Explanation
Every PMLC model — whether Linear (Waterfall), Incremental, Iterative, Adaptive, or Extreme — follows a defined sequence of phases such as Scoping, Planning, Launching, Monitoring & Controlling, and Closing. While the emphasis and iteration frequency differ across models, the presence of a sequenced phase structure is a universal characteristic of all PMLC models.