PMI-ACP · Question #527
Which of the following is a weakness of an Adaptive PMLC Model?
The correct answer is C. Cannot identify what will be delivered at the end of the project. Adaptive PMLC models (e.g., Agile approaches) are designed for high-uncertainty environments where requirements are unclear or frequently changing. This flexibility is also their primary weakness: because requirements evolve iteratively, it is impossible to commit to a fully…
Question
Which of the following is a weakness of an Adaptive PMLC Model?
Options
- ADoes not waste time on non-value-added work
- BDoes not waste time planning uncertainty
- CCannot identify what will be delivered at the end of the project
- DAvoids all management issues processing scope change requests
How the community answered
(39 responses)- A5% (2)
- B3% (1)
- C92% (36)
Explanation
Adaptive PMLC models (e.g., Agile approaches) are designed for high-uncertainty environments where requirements are unclear or frequently changing. This flexibility is also their primary weakness: because requirements evolve iteratively, it is impossible to commit to a fully defined end-state deliverable at project inception. Stakeholders and sponsors may find this lack of predictability uncomfortable. The other options (A, B, D) are actually strengths of adaptive approaches, not weaknesses.
Topics
Community Discussion
No community discussion yet for this question.