Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for sco

The correct answer is D. Both teams have estimated the project to be of same size.. Team A estimate is 420/30 = 14 sprints to complete the project. Team B estimate is 280/20=14 sprints to complete the project.

Submitted by saadiq_pk· Apr 18, 2026Adaptive Planning

Question

Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks. What can an agile practitioner conclude about team A and team B's estimates?

Options

  • ATeam B has underestimated scope compared to team A.
  • BTeam A is more confident in delivering velocity than team B.
  • CBoth teams need to indicate their proposed technology before the estimates can be analyzed.
  • DBoth teams have estimated the project to be of same size.

How the community answered

(67 responses)
  • A
    18% (12)
  • B
    4% (3)
  • C
    6% (4)
  • D
    72% (48)

Explanation

Team A estimate is 420/30 = 14 sprints to complete the project. Team B estimate is 280/20=14 sprints to complete the project.

Topics

#Story Points#Velocity#Estimation#Adaptive Planning