PMI-ACP · Question #723
Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for sco
The correct answer is D. Both teams have estimated the project to be of same size.. Team A estimate is 420/30 = 14 sprints to complete the project. Team B estimate is 280/20=14 sprints to complete the project.
Question
Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks. What can an agile practitioner conclude about team A and team B's estimates?
Options
- ATeam B has underestimated scope compared to team A.
- BTeam A is more confident in delivering velocity than team B.
- CBoth teams need to indicate their proposed technology before the estimates can be analyzed.
- DBoth teams have estimated the project to be of same size.
How the community answered
(67 responses)- A18% (12)
- B4% (3)
- C6% (4)
- D72% (48)
Explanation
Team A estimate is 420/30 = 14 sprints to complete the project. Team B estimate is 280/20=14 sprints to complete the project.