PMI-ACP · Question #724
PMI-ACP Question #724: Real Exam Question with Answer & Explanation
The correct answer is D: Help establish the next sprint's goal.. Sprint planning begins with establishing the sprint goal, which defines the purpose and focus of the iteration. The sprint goal provides the 'why' that guides all subsequent decisions — which stories to select, how to decompose them into tasks, and how to estimate effort. Witho
Question
What is the first thing an agile development team should do when planning an iteration?
Options
- AAssign the tasks to one team member.
- BSeparate the stories into tasks.
- CEstimate the stories' tasks.
- DHelp establish the next sprint's goal.
Explanation
Sprint planning begins with establishing the sprint goal, which defines the purpose and focus of the iteration. The sprint goal provides the 'why' that guides all subsequent decisions — which stories to select, how to decompose them into tasks, and how to estimate effort. Without a clear goal, story selection and task breakdown lack context and direction. Assigning tasks (A), separating stories into tasks (B), and estimating tasks (C) all come after the goal is established.
Topics
Community Discussion
No community discussion yet for this question.