Which of the following 2 statements are TRUE about Product Refinement? (Choose two.)

The correct answer is A. Should take no more than 10% of the Development Team's time C. Multiple Scrum Teams may participate in this process. Product Backlog Refinement should consume no more than 10% of the Development Team's capacity in a Sprint, ensuring it does not overwhelm delivery work (A). Multiple Scrum Teams working on the same product may collaboratively participate in refinement sessions to align on shared

Submitted by ahmad_uae· Apr 18, 2026Adaptive Planning

Question

Which of the following 2 statements are TRUE about Product Refinement? (Choose two.)

Options

  • AShould take no more than 10% of the Development Team's time
  • BThe Scrum Master facilitates these sessions
  • CMultiple Scrum Teams may participate in this process
  • DThe Product Owner is responsible for all estimates

How the community answered

(15 responses)
  • A
    93% (14)
  • D
    7% (1)

Explanation

Product Backlog Refinement should consume no more than 10% of the Development Team's capacity in a Sprint, ensuring it does not overwhelm delivery work (A). Multiple Scrum Teams working on the same product may collaboratively participate in refinement sessions to align on shared backlog items (C). Choice B is incorrect because refinement is typically facilitated by the Product Owner and Development Team together - there is no Scrum rule that the Scrum Master facilitates these sessions. Choice D is incorrect because the Development Team (not the Product Owner) is responsible for all estimates, as they are the ones doing the work.