PMI-ACP · Question #479
Which of the following 2 statements are TRUE about Product Refinement? (Choose two.)
The correct answer is A. Should take no more than 10% of the Development Team's time C. Multiple Scrum Teams may participate in this process. Product Backlog Refinement should consume no more than 10% of the Development Team's capacity in a Sprint, ensuring it does not overwhelm delivery work (A). Multiple Scrum Teams working on the same product may collaboratively participate in refinement sessions to align on shared
Question
Which of the following 2 statements are TRUE about Product Refinement? (Choose two.)
Options
- AShould take no more than 10% of the Development Team's time
- BThe Scrum Master facilitates these sessions
- CMultiple Scrum Teams may participate in this process
- DThe Product Owner is responsible for all estimates
How the community answered
(15 responses)- A93% (14)
- D7% (1)
Explanation
Product Backlog Refinement should consume no more than 10% of the Development Team's capacity in a Sprint, ensuring it does not overwhelm delivery work (A). Multiple Scrum Teams working on the same product may collaboratively participate in refinement sessions to align on shared backlog items (C). Choice B is incorrect because refinement is typically facilitated by the Product Owner and Development Team together - there is no Scrum rule that the Scrum Master facilitates these sessions. Choice D is incorrect because the Development Team (not the Product Owner) is responsible for all estimates, as they are the ones doing the work.
Topics
Community Discussion
No community discussion yet for this question.