PMI-ACP · Question #480
PMI-ACP Question #480: Real Exam Question with Answer & Explanation
The correct answer is C: The Product Owner. The Product Owner is responsible for tracking the total work remaining in the Product Backlog at every Sprint Review. They use this information — often visualized as a release burndown chart — to project progress toward the product goal and forecast likely completion. While t
Question
Who tracks work remaining in the Product Backlog?
Options
- AThe Development Team
- BThe Scrum Master
- CThe Product Owner
- DSenior Executives
Explanation
The Product Owner is responsible for tracking the total work remaining in the Product Backlog at every Sprint Review. They use this information — often visualized as a release burndown chart — to project progress toward the product goal and forecast likely completion. While the Development Team tracks Sprint-level progress (Sprint Burndown), the Product Owner maintains visibility over the broader backlog. The Scrum Master and Senior Executives do not own this tracking responsibility.
Topics
Community Discussion
No community discussion yet for this question.