Who tracks work remaining in the Product Backlog?

The correct answer is C. The Product Owner. The Product Owner is responsible for tracking the total work remaining in the Product Backlog at every Sprint Review. They use this information - often visualized as a release burndown chart - to project progress toward the product goal and forecast likely completion. While the…

Submitted by kim_seoul· Apr 18, 2026Value-driven Delivery

Question

Who tracks work remaining in the Product Backlog?

Options

  • AThe Development Team
  • BThe Scrum Master
  • CThe Product Owner
  • DSenior Executives

How the community answered

(48 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    92% (44)
  • D
    2% (1)

Explanation

The Product Owner is responsible for tracking the total work remaining in the Product Backlog at every Sprint Review. They use this information - often visualized as a release burndown chart - to project progress toward the product goal and forecast likely completion. While the Development Team tracks Sprint-level progress (Sprint Burndown), the Product Owner maintains visibility over the broader backlog. The Scrum Master and Senior Executives do not own this tracking responsibility.

Topics

#Product Owner#Product Backlog#Scrum Roles#Agile Responsibilities