nerdexam
PMIPMI

PMI-ACP · Question #480

PMI-ACP Question #480: Real Exam Question with Answer & Explanation

The correct answer is C: The Product Owner. The Product Owner is responsible for tracking the total work remaining in the Product Backlog at every Sprint Review. They use this information — often visualized as a release burndown chart — to project progress toward the product goal and forecast likely completion. While t

Submitted by kim_seoul· Apr 18, 2026Value-driven Delivery

Question

Who tracks work remaining in the Product Backlog?

Options

  • AThe Development Team
  • BThe Scrum Master
  • CThe Product Owner
  • DSenior Executives

Explanation

The Product Owner is responsible for tracking the total work remaining in the Product Backlog at every Sprint Review. They use this information — often visualized as a release burndown chart — to project progress toward the product goal and forecast likely completion. While the Development Team tracks Sprint-level progress (Sprint Burndown), the Product Owner maintains visibility over the broader backlog. The Scrum Master and Senior Executives do not own this tracking responsibility.

Topics

#Product Owner#Product Backlog#Scrum Roles#Agile Responsibilities

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions