PMI-ACP · Question #481
Who can change the Sprint Backlog during a Sprint?
The correct answer is D. The Development Team. The Sprint Backlog is owned exclusively by the Development Team. Only the Development Team can change it during a Sprint. It represents their plan for delivering the Sprint Goal, so they must have full authority over it. The Product Owner owns the Product Backlog (not the…
Question
Who can change the Sprint Backlog during a Sprint?
Options
- ASenior Executives
- BThe Product Owner
- CThe Scrum Master
- DThe Development Team
How the community answered
(30 responses)- A3% (1)
- B7% (2)
- D90% (27)
Explanation
The Sprint Backlog is owned exclusively by the Development Team. Only the Development Team can change it during a Sprint. It represents their plan for delivering the Sprint Goal, so they must have full authority over it. The Product Owner owns the Product Backlog (not the Sprint Backlog), the Scrum Master facilitates the process, and senior executives have no role in managing Sprint-level work.
Topics
Community Discussion
No community discussion yet for this question.