PMI-ACP · Question #722
PMI-ACP Question #722: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #722. The question stem and answer options stay visible for context.
Submitted by katya_ua· Apr 18, 2026Adaptive Planning
Question
An agile team is unable to complete all its planned sprint user stories, which results in a decrease of its planned sprint velocity. What should the team do?
Options
- ARe-estimate the sprint's completed stories to increase and adjust the sprint's velocity.
- BIncrease the duration of the next sprint to accommodate the incomplete user stories and maintain
- CWork with the product owner to create a spike with another agile team.
- DRe-estimate the incomplete stories for the next sprint because its relative size has changed.
Unlock PMI-ACP to see the answer
You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Sprint planning#Velocity#Story estimation#Backlog management