How can a scrum team obtain more feedback from a minimally responsive outside stakeholder?

The correct answer is A. Keep sprints short.. Shorter sprints create more frequent opportunities for review and feedback, lowering the commitment threshold for a busy or reluctant stakeholder. If a stakeholder is minimally responsive, they are unlikely to engage for a 6-week sprint but may participate in a 1-week sprint revi

Submitted by andreas_gr· Apr 18, 2026Stakeholder Engagement

Question

How can a scrum team obtain more feedback from a minimally responsive outside stakeholder?

Options

  • AKeep sprints short.
  • BInvite the stakeholder to the daily stand ups.
  • CAsk the stakeholder for estimates for each user story.
  • DSchedule more demos during each sprint.

How the community answered

(46 responses)
  • A
    80% (37)
  • B
    11% (5)
  • C
    2% (1)
  • D
    7% (3)

Explanation

Shorter sprints create more frequent opportunities for review and feedback, lowering the commitment threshold for a busy or reluctant stakeholder. If a stakeholder is minimally responsive, they are unlikely to engage for a 6-week sprint but may participate in a 1-week sprint review. Inviting them to daily standups (B) is too much of a time commitment and standups are for the team. Asking for story estimates (C) is outside a stakeholder's typical role. Scheduling more demos within a sprint (D) increases frequency but also increases the ask - shorter sprints achieve the same result more naturally.