nerdexam
PMI

PMI-ACP · Question #703

A product owner adds a 21-point, high-priority story to a sprint backlog. The team is concerned that it cannot be completed during the current sprint. What should the team do?

Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #703. The question stem and answer options stay visible for context.

Submitted by skyler.x· Apr 18, 2026Adaptive Planning

Question

A product owner adds a 21-point, high-priority story to a sprint backlog. The team is concerned that it cannot be completed during the current sprint. What should the team do?

Options

  • AAdvise the product owner that the story will have to wait until the next sprint.
  • BWork extra hours to complete the story and satisfy the customer's requirements.
  • CBreak down the story into smaller increments and negotiate other stories on the sprint backlog.
  • DIncrease the length of the sprint to accommodate the story.

Unlock PMI-ACP to see the answer

You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Story splitting#Sprint backlog management#Capacity planning#PO collaboration
Full PMI-ACP Practice