The correct answer is B: Information radiators.. Information radiators are large, highly visible displays (physical boards or screens) that broadcast real-time project status to anyone who walks by — team members, stakeholders, and management. Velocity charts, burndown charts, storyboards, and impediment lists are classic exa

Submitted by layla.eg· Apr 18, 2026Stakeholder Engagement

Question

The velocity chart, storyboard, burndown chart, and impediment list are often communicated using:

Options

  • AStatus reports.
  • BInformation radiators.
  • CPortfolio presentations.
  • DProject data packages.

Explanation

Information radiators are large, highly visible displays (physical boards or screens) that broadcast real-time project status to anyone who walks by — team members, stakeholders, and management. Velocity charts, burndown charts, storyboards, and impediment lists are classic examples of information radiators because they make team progress and blockers immediately visible without requiring a formal report. Option A (status reports) is a traditional, document-based communication. Options C and D are formal presentation or documentation formats, not agile transparency tools.

Topics

#Information radiators#Agile communication#Visual management#Transparency

Community Discussion

No community discussion yet for this question.