PMI-ACP · Question #72

In Agile projects, how are planning outputs shared with stakeholders?

The correct answer is A. Using the most highly visible method possible. In Agile, transparency is a core value. Planning outputs such as backlogs, iteration plans, and velocity charts should be shared using the most highly visible method possible - such as physical or digital information radiators visible to the entire team and stakeholders. This…

Submitted by yousef_jo· Apr 18, 2026Stakeholder Engagement

Question

In Agile projects, how are planning outputs shared with stakeholders?

Options

  • AUsing the most highly visible method possible
  • BOn a need-to-know basis depending on role
  • CAccording to the project communications plan
  • DThrough a series of stakeholder meetings

How the community answered

(36 responses)
  • A
    94% (34)
  • B
    3% (1)
  • D
    3% (1)

Explanation

In Agile, transparency is a core value. Planning outputs such as backlogs, iteration plans, and velocity charts should be shared using the most highly visible method possible - such as physical or digital information radiators visible to the entire team and stakeholders. This promotes openness, trust, and continuous feedback. Restricting information on a need-to-know basis or limiting sharing to formal meetings goes against Agile's transparency principle.

Topics

#Agile Communication#Transparency#Information Radiators#Stakeholder Engagement

Community Discussion