PMI-ACP · Question #684
An executive requests information regarding a sprint status. What action should the product owner take?
The correct answer is B. Direct the executive to the information radiator. Information radiators (e.g., task boards, burndown charts, sprint walls) are a core agile transparency tool - they make project status continuously visible to anyone, including executives, without requiring a dedicated meeting or report. Option B is correct because directing…
Question
An executive requests information regarding a sprint status. What action should the product owner take?
Options
- AInvite the executive to the standup.
- BDirect the executive to the information radiator.
- CPersonally meet with the executive.
- DEmail the requested information to the executive.
How the community answered
(33 responses)- A12% (4)
- B79% (26)
- C6% (2)
- D3% (1)
Explanation
Information radiators (e.g., task boards, burndown charts, sprint walls) are a core agile transparency tool - they make project status continuously visible to anyone, including executives, without requiring a dedicated meeting or report. Option B is correct because directing the executive to the information radiator respects agile's principle of transparency while being efficient. Option A (inviting to standup) could disrupt the team's focused daily sync. Option C (personal meeting) is inefficient when the information is already publicly displayed. Option D (emailing information) creates redundant reporting overhead and is not necessary if a radiator already exists.