PMI-ACP · Question #674
PMI-ACP Question #674: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #674. The question stem and answer options stay visible for context.
Submitted by thandi_sa· Apr 18, 2026Problem Detection and Resolution
Question
A member of the development team is working on a prioritized non-functional requirement involving integrating with a 3rd party system. This integration has not been done before on the project. What should the project leader suggest?
Options
- ADevelop and document a detailed architectural design, peer review with the development team,
- BDevelop the functional requirements of the solution first before any non-functional requirement, as
- CDiscuss the integration requirement with the product owner and negotiate it to be lower on the
- DDevelop and test the implementation approach and demonstrate it at the next sprint review to
Unlock PMI-ACP to see the answer
You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Agile Spikes#Non-functional Requirements#Risk Management#Technical Exploration