PMI-ACP · Question #296
While developing a story during the iteration, team discovered new tasks that were not identified earlier. A newly discovered task is such that the User Story cannot be completed during the…
The correct answer is B. Story 1, 2, and 4. When a newly discovered task prevents a User Story from completing within the iteration, the team should: (1) immediately notify the Product Owner, (2) attempt to split the story and deliver the completable portion, and (3) return the unfinished work to the Product Backlog for…
Question
While developing a story during the iteration, team discovered new tasks that were not identified earlier. A newly discovered task is such that the User Story cannot be completed during the iterations. What are the most appropriate actions for the team to perform?
Options
- AStory 1, 2, and 3
- BStory 1, 2, and 4
- CStory 1 and 2
- DStory 2, 3, and 4
How the community answered
(35 responses)- A9% (3)
- B83% (29)
- C3% (1)
- D6% (2)
Explanation
When a newly discovered task prevents a User Story from completing within the iteration, the team should: (1) immediately notify the Product Owner, (2) attempt to split the story and deliver the completable portion, and (3) return the unfinished work to the Product Backlog for re-prioritization in the next sprint. The stated correct answer B - 'Story 1, 2, and 4' - references a prioritized story list that is not included in the question stem, making this question incomplete as presented. The general principle is: do not force incomplete work, communicate transparently, and re-plan collaboratively.
Topics
Community Discussion