nerdexam
PMI

PMI-ACP · Question #296

While developing a story during the iteration, team discovered new tasks that were not identified earlier. A newly discovered task is such that the User Story cannot be completed during the…

The correct answer is B. Story 1, 2, and 4. When a newly discovered task prevents a User Story from completing within the iteration, the team should: (1) immediately notify the Product Owner, (2) attempt to split the story and deliver the completable portion, and (3) return the unfinished work to the Product Backlog for…

Submitted by hans_de· Apr 18, 2026Problem Detection and Resolution

Question

While developing a story during the iteration, team discovered new tasks that were not identified earlier. A newly discovered task is such that the User Story cannot be completed during the iterations. What are the most appropriate actions for the team to perform?

Options

  • AStory 1, 2, and 3
  • BStory 1, 2, and 4
  • CStory 1 and 2
  • DStory 2, 3, and 4

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    83% (29)
  • C
    3% (1)
  • D
    6% (2)

Explanation

When a newly discovered task prevents a User Story from completing within the iteration, the team should: (1) immediately notify the Product Owner, (2) attempt to split the story and deliver the completable portion, and (3) return the unfinished work to the Product Backlog for re-prioritization in the next sprint. The stated correct answer B - 'Story 1, 2, and 4' - references a prioritized story list that is not included in the question stem, making this question incomplete as presented. The general principle is: do not force incomplete work, communicate transparently, and re-plan collaboratively.

Topics

#Iteration Management#Scope Management#Product Owner Collaboration#Adaptive Planning