The correct answer is B: Review possible options and make an informed decision to cut losses based on delivered. Agile embraces empirical decision-making. Rather than reacting impulsively (terminating the project outright, as in A) or blindly continuing (D), the product owner should review all available options — including the business value already delivered, the cost to fix the feature,

Submitted by diego_uy· Apr 18, 2026Problem Detection and Resolution

Question

Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected. What should the product owner do?

Options

  • ATerminate the project to cut losses
  • BReview possible options and make an informed decision to cut losses based on delivered
  • CBring in experts to increase the probability of success
  • DContinue the project, release the product without the failing feature, and fix the feature in a

Explanation

Agile embraces empirical decision-making. Rather than reacting impulsively (terminating the project outright, as in A) or blindly continuing (D), the product owner should review all available options — including the business value already delivered, the cost to fix the feature, and the impact of releasing without it — and then make an informed, data-driven decision. Option A (terminate immediately) doesn't consider already-delivered value. Option C (bring in experts) might be one option evaluated, but it's not a decision framework. Option D ignores the critical failure and risks releasing a defective product. Option B is the only response that reflects sound agile judgment.

Topics

#Product Owner Role#Problem Resolution#Risk Response#Strategic Decision Making