PMI-ACP · Question #667
PMI-ACP Question #667: Real Exam Question with Answer & Explanation
The correct answer is B: Review possible options and make an informed decision to cut losses based on delivered. Agile embraces empirical decision-making. Rather than reacting impulsively (terminating the project outright, as in A) or blindly continuing (D), the product owner should review all available options — including the business value already delivered, the cost to fix the feature,
Question
Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected. What should the product owner do?
Options
- ATerminate the project to cut losses
- BReview possible options and make an informed decision to cut losses based on delivered
- CBring in experts to increase the probability of success
- DContinue the project, release the product without the failing feature, and fix the feature in a
Explanation
Agile embraces empirical decision-making. Rather than reacting impulsively (terminating the project outright, as in A) or blindly continuing (D), the product owner should review all available options — including the business value already delivered, the cost to fix the feature, and the impact of releasing without it — and then make an informed, data-driven decision. Option A (terminate immediately) doesn't consider already-delivered value. Option C (bring in experts) might be one option evaluated, but it's not a decision framework. Option D ignores the critical failure and risks releasing a defective product. Option B is the only response that reflects sound agile judgment.