PMI-ACP · Question #673
PMI-ACP Question #673: Real Exam Question with Answer & Explanation
The correct answer is B: Ask the team for suggestions. The team ultimately owns the work and is self-organized. While offering the team member encouragement to meet commitments is a good thing, the most effective way to ensure the team can meet the sprint goal is to be transparent with the team about the other member falling behind i
Question
What should a Scrum Master do when one team member falls behind in their tasks?
Options
- AMove the task to another team member who has spare capacity in the sprint
- BAsk the team for suggestions
- CPrivately offer the team member encouragement to meet task commitments
- DNotify the product owner
Explanation
The team ultimately owns the work and is self-organized. While offering the team member encouragement to meet commitments is a good thing, the most effective way to ensure the team can meet the sprint goal is to be transparent with the team about the other member falling behind in tasks. That way they can figure out a strategy to get things back on track.
Topics