nerdexam
PMIPMI

PMI-ACP · Question #673

PMI-ACP Question #673: Real Exam Question with Answer & Explanation

The correct answer is B: Ask the team for suggestions. The team ultimately owns the work and is self-organized. While offering the team member encouragement to meet commitments is a good thing, the most effective way to ensure the team can meet the sprint goal is to be transparent with the team about the other member falling behind i

Submitted by valeria.br· Apr 18, 2026Team Performance

Question

What should a Scrum Master do when one team member falls behind in their tasks?

Options

  • AMove the task to another team member who has spare capacity in the sprint
  • BAsk the team for suggestions
  • CPrivately offer the team member encouragement to meet task commitments
  • DNotify the product owner

Explanation

The team ultimately owns the work and is self-organized. While offering the team member encouragement to meet commitments is a good thing, the most effective way to ensure the team can meet the sprint goal is to be transparent with the team about the other member falling behind in tasks. That way they can figure out a strategy to get things back on track.

Topics

#Scrum Master Role#Team Self-Organization#Impediment Resolution#Team Collaboration

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions