Question
Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project. What should the product owner do next?
Options
- AObtain approval from the change control board to discontinue the component
- BAsk the team to continue developing the component
- CAsk the team to discontinue developing the component
- DRequest the sponsor's formal approval to discontinue the component