nerdexam
PMIPMI

PMI-ACP · Question #671

PMI-ACP Question #671: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #671. The question stem and answer options stay visible for context.

Submitted by yuriko_h· Apr 18, 2026Value-driven Delivery

Question

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project. What should the product owner do next?

Options

  • AObtain approval from the change control board to discontinue the component
  • BAsk the team to continue developing the component
  • CAsk the team to discontinue developing the component
  • DRequest the sponsor's formal approval to discontinue the component

Unlock PMI-ACP to see the answer

You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Product Owner role#Value maximization#Waste reduction#Adaptive scope
Full PMI-ACP PracticeBrowse All PMI-ACP Questions