PMI-ACP · Question #670
How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?
The correct answer is D. Facilitate a product development roadmap workshop. A product development roadmap workshop brings all key stakeholders together in an active, collaborative session to jointly shape the product vision, priorities, and direction. This is the most effective way to ensure proper stakeholder engagement in planning because it is…
Question
How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?
Options
- ACollect stakeholder requirements
- BConduct an iteration planning meeting
- CCommunicate product backlog items to the stakeholders
- DFacilitate a product development roadmap workshop
How the community answered
(40 responses)- A13% (5)
- B8% (3)
- C3% (1)
- D78% (31)
Explanation
A product development roadmap workshop brings all key stakeholders together in an active, collaborative session to jointly shape the product vision, priorities, and direction. This is the most effective way to ensure proper stakeholder engagement in planning because it is participatory - stakeholders contribute to the plan rather than simply receiving information. Option A (collecting requirements) is a passive, one-directional, and waterfall-style activity. Option B (iteration planning) is an internal team ceremony not typically open to all stakeholders. Option C (communicating backlog items) is one-way information sharing, not engagement. True engagement means stakeholders have a voice in shaping the plan, which is what a facilitated workshop delivers.
Topics
Community Discussion
No community discussion yet for this question.