PMI-ACP · Question #687

An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a…

The correct answer is C. Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve. In Scrum and agile frameworks, the retrospective is the dedicated ceremony for the team to inspect their own process and adapt. When velocity is lower than expected, the team must use the retrospective to analyze the root causes (e.g., estimation errors, impediments, skill…

Submitted by brentm· Apr 18, 2026Problem Detection and Resolution

Question

An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a critical release date without corrective action. What should the team do?

Options

  • ACollaborate with the product owner to reprioritize the product backlog, thus ensuring that more
  • BAsk the team lead to calculate the team's target velocity according to the project plan, and assign
  • CFocus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve
  • DReestimate the backlog items from the release, ensuring that contingency is included to set

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    80% (28)
  • D
    11% (4)

Explanation

In Scrum and agile frameworks, the retrospective is the dedicated ceremony for the team to inspect their own process and adapt. When velocity is lower than expected, the team must use the retrospective to analyze the root causes (e.g., estimation errors, impediments, skill gaps) and agree on corrective actions. Option A is partly relevant but backlog reprioritization is the product owner's responsibility and doesn't address process improvement. Option B violates agile's self-organizing team principle by assigning work top-down based on a calculated 'target velocity.' Option D masks the problem by inflating estimates rather than fixing the underlying process issue.

Topics

#Velocity management#Retrospective#Corrective action#Agile forecasting