PMI-ACP · Question #678
During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision. The stakeholder asks for detailed requirements, design, and delivery p
The correct answer is B. Set expectations regarding the appropriate level of details requested during this stage. Agile embraces progressive elaboration - detailed requirements and plans emerge iteratively over time rather than being defined upfront. Option B is correct because the practitioner should educate and set realistic expectations: inception is about alignment on vision, goals, and
Question
During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision. The stakeholder asks for detailed requirements, design, and delivery plans. What should the agile practitioner do?
Options
- AProvide all information requested by the stakeholder
- BSet expectations regarding the appropriate level of details requested during this stage
- CInform the stakeholder that no detailed documents are provided using agile practices
- DAsk the team to supply the information to the stakeholder
How the community answered
(32 responses)- A3% (1)
- B84% (27)
- C9% (3)
- D3% (1)
Explanation
Agile embraces progressive elaboration - detailed requirements and plans emerge iteratively over time rather than being defined upfront. Option B is correct because the practitioner should educate and set realistic expectations: inception is about alignment on vision, goals, and high-level scope, not detailed specifications. Option A would produce documentation that will likely change and waste effort. Option C is too absolute and dismissive - some documentation is produced in agile, just at the right level at the right time. Option D delegates to the team without addressing the stakeholder's misunderstanding of agile's approach to early-stage planning.